27 June 2011 ~ 0 Comments

Construction Notice for Maiden Lane

Construction Notice Construction activity for utility relocation will begin excavating on Maiden Lane on the east side of Stockton Street between Post and Geary streets on July 5, 2011 Contract Number 1251 Project Description On Tuesday, July 5 Synergy Project Management, the contractor, will begin to excavate under streets in preparation for utility relocation required […]

Continue Reading

12 May 2011 ~ 0 Comments

Paving 4th Street on Friday, May 13

Utility relocation for the Moscone/Portal Station Paving on 4th Street will begin on Friday, May 13, 2011! ((PDF available: Contract 1250 Moscone/Portal Station) Synergy Project Management (Contractor) will soon be completing utility relocation for the future Moscone Station and Portal construction on 4th Street between Howard to Bryant streets. The final phase of this task […]

Continue Reading

10 January 2011 ~ 0 Comments

UMS Utility Relocation Meeting with BID

Central Subway representatives met with the Union Square Business Improvement District (BID) last Thursday to speak on the upcoming utility relocation for the Union Square/Market Street Station (UMS). The presentation for the BID focused on what should be expected during construction and the protocols that the contractor will be following during the UMS utility relocation […]

Continue Reading

02 December 2010 ~ 2 Comments

Later Construction Hours until Dec. 17

For the next 2 weeks, expect delays along Fourth Street and please take alternative routes when possible.  Utility relocation has been extended approximately until 5:30p.m.  and additional construction activities will occur on Saturdays (Dec. 4 and Dec. 11).  Construction activities will stop from Dec. 20 through Dec. 31 but will resume on Monday, Jan. 3, […]

Continue Reading

23 April 2010 ~ 1 Comment

Important re-route information

For those of you who haven’t heard about the re-routing on the 30 Stockton and 45 Union/Stockton, here’s an update! This re-route is required due to ongoing utilities relocation and underpinning work at 401 Fourth Street to shore up the foundation. The 30 Stockton and 45 Union/Stockton are being re-routed, while the street is not […]

Continue Reading

26 March 2010 ~ 3 Comments

Utility Relocation on the move…

Synergy Project Management began the installation of sewer line and manholes along Clementina between Fourth and Fifth streets. Traffic is being re-routed while sewer work is being performed on Clementina Street.  Clementina Street will be closed during the actual work period, Monday-Friday from 7:00 a.m.-3:00 p.m. A detour sign has been posted at Clementina and […]

Continue Reading

15 March 2010 ~ 0 Comments

Utilities Relocation Progress

Synergy’s work on utilities relocation is moving along. The installation of sewer and low pressure water lines, excavation for joint trench and dry utility vaults are ongoing at various locations. Phoenix Electric (subcontractor) has begun laying conduits for the joint trenches along various locations within the route. The coring through the Moscone Center wall has […]

Continue Reading

17 February 2010 ~ 2 Comments

Welcome Synergy Project Management!

Here’s the contractor who’s working on the utility relocation contract for the future Moscone Station and  Portal Tunnel on Fourth Street between Howard to Bryant Streets. Utility relocation work will be performed from January 2010 to approximately June 2011. Synergy Project Management, Inc. (SPM), a local San Francisco business with years of experience in construction and engineering began utility relocation […]

Continue Reading